A slightly wet afternoon...
Despite the dampness progress is still being made on the pool!! Today the installation of the glass around the main entrance has commenced and the vast majority completed. Starting to look very much like the entrance to the new pool.
Also, the exterior cladding is nearing completion - 85% of it has been applied around the building with only the deep end side of the main pool and the slide tower left to be done. The main pool side should be done by the end of the week and the slide tower will be completed once the slide pillar and stairs are installed.
Seems like everyday little pots of progress are showing up. Other notables on the interior include the brickwork being completed in the changerooms and staff change areas.
Look for more updates tomorrow!!