Well, today was the day to transfer the air handling units from outside of the pool to inside and up on the second floor of the mechanical area of the facility.
I showed up at the pool around 12noon, at that point they had transitioned the first air handling unit to the main pool deck from outside. Over the course of the next three hours this unit then made its way, through excellent communication from all those in attendance and a steady hand on the crane controls to the second story.
This work involved two cranes, one to move the units from outside to inside the facility and a second to move from the main floor (pool deck) to the second story (which was placed inside the building in advance of the air handling units being moved it.
I showed up at the pool around 12noon, at that point they had transitioned the first air handling unit to the main pool deck from outside. Over the course of the next three hours this unit then made its way, through excellent communication from all those in attendance and a steady hand on the crane controls to the second story.
This is another area that we will continue to post updates on as the air handling system slowly comes to life over the upcoming months.
Enjoy your Saturday!
The Pool Guy.