Good afternoon everyone,
I hope that you have all been enjoying the break in weather as much as I have. Another week finishing, another week closer to opening!
Well let's get down to it.
The first photo and the third photo below are showing the ducting for the air handling being installed over the Lap pool. In the third photo you can see that the workers have lifted a section of ducting up to the ceiling support from the fitness room on the upper floor and are starting to slide it along. The first photo shows the ducting lining up with the duct that is already in place.
In the second photo (below) is a picture of our emergency generator set in place adjacent to the mechanical room. This generator will be used as a back up during power failures.
And in the photo below you can see the mezzanine floor of the mechanical room. The room on the left is the "Nuts & bolts" of the operation (my office - complete with window!), the room on the right is the chemical room. These rooms and the electrical room walls were blocked in during the past week or so.
That the update for this week. Next week we are planning to pour the decks at the shallow end and north side of the wave pool. Photos to follow!
Have a good one.